Pre-Lift Tool Box Meeting (TBM) and Safety Briefing Before Crane Operations

This morning, the crane hoists rebar bundles onto the fifth-floor deck. Before operations commence, you lead a Tool Box Meeting (TBM) with Yamamoto, the subcontractor rigging foreman: assigning slinging and signaling duties, demarcating the exclusion zone, and agreeing on suspension criteria.

Me

Now, let us begin the Tool Box Meeting (TBM). This morning, we will hoist rebar bundles onto the 5th floor slab using the crane.

Me

Who will be in charge of rigging/slinging and signaling?

Other (T)

Rigging will be handled by Tanaka and Sato, and I will perform signaling duties. Both riggers are certified qualification holders.

Me

Understood. You have already submitted copies of their qualification certificates, right?

Other (T)

Yes, we submitted them last week.

Me

Here is today critical danger point: absolutely never enter beneath a suspended load.

Me

We will cordone off the crane slewing radius with traffic cones as a strict no-entry zone. We will post one traffic coordinator along the access path.

Other (T)

If the wind becomes strong, what should we do?

Me

In that event, we will immediately shut down operations. Let the decision be made jointly through consultation between Yamamoto-san and myself.

Other (T)

Understood. I will communicate with the crane operator via two-way radio.

Me

Yes. Please ensure signaling calls are loud, clear, and distinct.

Me

Let today action target be: "Never enter beneath suspended loads, OK!"

Other (T)

Never enter beneath suspended loads, OK!

Key Patterns

  • Inquiring about assigned operational responsibilities within the team
  • Strictly and unconditionally prohibiting entry into a hazardous zone
  • Establishing operational shutdown criteria in advance of risky work
  • Rallying the team behind a shared procedural slogan or action target