Construction Japanese · 天井内の取り合いを設備業者と調整する

Coordinating Ceiling Plenum Clashes with the MEP Subcontractor

The composite coordination drawing reveals that the duct and the drainage pipe clash within the 4th floor corridor ceiling void, directly beneath the beam. You meet with the MEP contractor engineer to reroute the conduits, establish scope demarcations, and set drawing delivery dates.

Me

Inside the corridor ceiling void on the 4th floor, looking at the composite drawing, the duct and the drainage pipe are colliding with each other.

Other (S)

Ah, that is the area beneath the beam. The ceiling plenum space is insufficient.

Me

Because the finished ceiling height cannot be altered, our only option is to reroute one of them.

Other (S)

Drainage piping has a required slope, so it cannot be relocated. I intend to flatten the duct profile and offset it sideways.

Me

In that case, will the inspection access hatch position also shift?

Other (S)

Yes, it will shift slightly. I will coordinate with the interior finishing contractor so that it aligns with the ceiling tile grid.

Me

Please allow me to confirm construction scope demarcation as well. The duct hanger suspension bolts fall under your company work scope, correct?

Other (S)

That is correct. Concrete inserts were already cast in place during slab placement.

Me

That is very helpful. Could you provide the revised composite drawing by Friday? Next week, let us hold another meeting on interface coordination.

Other (S)

Understood. I will cross-check the electrical cable trays simultaneously.

Key Patterns

  • Indicating a physical clash discovered when reviewing composite drawings
  • Stating a fixed structural constraint and the single viable workaround
  • Verifying whether a specific task belongs to the counterparty trade scope
  • Requesting submittal of revised technical documentation by a fixed deadline