Construction Japanese · 打設前にスリーブを設備業者と確認する

Confirming Sleeve Penetrations with the MEP Subcontractor

A few days prior to the concrete slab pour, you and the MEP subcontractor lead cross-check pipe sleeve penetrations through beams, discovering a discrepancy between the construction shop drawings and the latest MEP drawings.

Me

Before Thursday concrete pour, please allow me to confirm the sleeve penetration positions.

Other (S)

Yes, here are the construction shop drawings.

Me

Regarding the sleeve penetrating this beam, the mechanical drawing indicates a diameter of 150, but the shop drawing says 100.

Other (S)

Ah, that is true. The mechanical drawing is the latest version. Last week, the air conditioning piping size was enlarged.

Me

Opening a 150 hole in this beam may impact structural integrity. We need confirmation from the structural designer.

Other (S)

If we add supplemental reinforcement rebar, I think it should be fine though...

Me

Just to be safe, I will confirm with the design supervisor. Until we receive an answer, please put this sleeve alone on hold.

Other (S)

Understood. For the other sleeves, we will proceed according to the shop drawings.

Me

Once sleeve fastening is complete, please take photos and send them to me. If they shift during concrete placement, we cannot fix them later.

Other (S)

Understood. By when should I send them?

Me

Please send them by 3 PM on Wednesday. After that, I will conduct the final verification inspection on site.

Other (S)

Understood. As soon as you hear back from the supervisor, please let me know immediately.

Key Patterns

  • Polite expression requesting permission to inspect or verify an item
  • Formula for highlighting a discrepancy between two reference drawings
  • Indicating that one will consult an authority to be certain before acting
  • Requesting that a specific work item be placed on hold until an answer arrives