Email Requesting a Cost Quotation from a Subcontractor (Request for Quotation / RFQ)

Japanese Text

件名:【見積依頼】〔工事名〕〔内装工事〕

〔〇〇工業株式会社〕
〔〇〇〕様

いつもお世話になっております。
〔会社名〕〔工事名〕作業所の〔名前〕です。

標記の件につきまして、下記の条件でお見積もりをお願いいたします。

■工事場所
〔東京都〇〇区〇〇〕

■見積範囲
〔例:3~5階 内装工事一式(軽量鉄骨下地、ボード張り、クロス張り)〕

■工期(予定)
〔〇月〇日〕~〔〇月〇日〕

■見積条件
・足場、揚重:〔例:当社負担〕
・産業廃棄物の処分:〔例:貴社負担〕
・作業時間:〔例:8時~17時(日曜・祝日は休工)〕

■添付資料
〔例:意匠図一式、仕上表、工程表〕

■提出期限
〔〇月〇日(〇)〕

お見積書には、内訳書を添付していただきますようお願いいたします。
ご不明な点がございましたら、〔〇月〇日〕までにご質問ください。
現地確認をご希望の場合も、お気軽にご連絡ください。

ご多忙のところ恐縮ですが、どうぞよろしくお願いいたします。

Structure Breakdown

The subject line features the tag [Request for Quotation], project name, and trade specialty, enabling trade contractors to file it under the proper tender folder.
The phrase 標記の件 refers to "the matter stated in the subject line". A concise business formula that gets straight to the request without repeating the project title.
State clearly what is included, on which floors, and up to which finish level. Ambiguous scopes result in missing cost items (見積落ち) and disparate estimating assumptions.
Define who provides scaffolding, crane lifts, and waste handling. The terms 当社 (our company) and 貴社 (your company) represent formal written correspondence.
Request an itemized breakdown rather than a single lump-sum figure. Detailed unit rates enable fair comparison across bidders and future change order adjustments.
Set an inquiry deadline a few days prior to the submittal due date so clarifications can be answered uniformly for all bidders simultaneously.
Invite subcontractors to inspect the physical site: site access, laydown zones, and logistics restrictions directly impact pricing. The phrase ご希望の場合 politely asks their preference.

English Translation

Subject: [Request for Quotation] [Interior Finishing Works] — [Project Name] [Subcontractor Co., Ltd.] Dear [Estimator/Representative Name] Thank you for your ongoing partnership. This is [Your Name] from the [Company Name] site office for [Project Name]. Regarding the subject matter, we request your cost quotation based on the conditions outlined below. ■ Construction Site Location [District Name, Tokyo] ■ Quotation Work Scope [Example: Lump-sum interior works for 3rd to 5th floors (lightweight steel framing, drywall boarding, wallpapering)] ■ Scheduled Construction Period [Month/Day] to [Month/Day] ■ Quotation Terms & Conditions ・Scaffolding and hoisting: [Example: Borne by General Contractor] ・Construction waste disposal: [Example: Borne by Subcontractor] ・Working hours: [Example: 8:00 AM to 5:00 PM (Closed Sundays and public holidays)] ■ Attached Tender Documents [Example: Architectural blueprints, finish schedule, construction master schedule] ■ Submittal Deadline [Month/Day (Day of Week)] Please ensure an itemized cost breakdown sheet is attached to your formal quotation. If you have any questions, please submit inquiries by [Month/Day]. If you wish to conduct an on-site walkthrough inspection, please feel free to contact us. We apologize for troubling you while you are busy, and we thank you for your cooperation.

Writing Tips & Notes

Send an identical package of tender drawings and contract conditions to all bidding subcontractors. Avoid unreasonably tight deadlines: Construction Business Act Article 20 Paragraph 3 and Cabinet Order Article 5-9 mandate statutory minimum estimating periods based on expected contract value—at least 1 day for under 5 million yen, at least 10 days for 5 to under 50 million yen, and at least 15 days for 50 million yen or more (the latter two may be shortened by up to 5 days only for force majeure). When quotations arrive, inspect the quotation conditions and items marked "separate" (別途) before looking at the total price.