Construction Japanese · 設計図書に関する質疑

Email Submitting a Drawing Clarification Query

Japanese Text

件名:【質疑】〔工事名〕No.〔〇〕〔2階 便所〕の床レベルについて

〔〇〇設計事務所〕
〔〇〇〕様

いつもお世話になっております。
〔会社名〕〔工事名〕作業所の〔名前〕です。

施工図を作成する中で、設計図書に食い違いがありましたので、下記のとおり質疑をお送りいたします。

■質疑No.
〔〇〕

■対象図面
〔例:A-201 2階平面図〕、〔例:S-202 2階梁伏図〕

■質疑内容
〔例:2階 便所の床について、意匠図ではスラブ下がり50mmとなっていますが、構造図には記載がありません。どちらを正とすればよろしいでしょうか。〕

■施工者案
〔例:床の排水勾配を確保するため、意匠図のとおりスラブを50mm下げて施工したいと考えております。〕

■回答希望日
〔〇月〇日〕まで(〔例:2階床の配筋に着手するため〕)

該当箇所に朱書きした図面を添付いたします。
お手数をおかけいたしますが、ご回答のほどよろしくお願いいたします。

Structure Breakdown

The subject line includes the tag [Query], the query number, and the location. With hundreds of queries on a project, consecutive numbering is essential for as-built records and dispute resolution.
The phrase お送りいたします is the humble form of 送ります. On site, people often say 質疑を出す, but emails to architects use this humble expression. If using a dedicated site RFI form attached to the email, write 質疑書を提出いたします.
Record the drawing number (図番) and title of ALL relevant drawings—discrepancies always exist between at least two documents.
The phrase 正とする means "to take as the standard/governing". A common question when two documents differ: "which should we follow?". Ask so the designer decides; never arbitrarily choose the contractor's preference.
The contractor's proposed solution, accompanied by the rationale. Providing a concrete proposal allows the designer to simply agree, which is far faster than leaving the question open-ended.
The deadline for a response and the operational reason (which work item is waiting). Without a clear deadline, queries tend to be deferred.
Attach the drawings with redlines (朱書き) around the queried location, so the designer does not have to search through the entire drawing set.

English Translation

Subject: [Query] [Project Name] No. [Number] Regarding Floor Level of [2nd Floor Restroom] [Design Office Co., Ltd.] Dear [Recipient Name] Thank you for your ongoing partnership. This is [Your Name] from the [Company Name] site office for [Project Name]. While preparing the construction shop drawings, a discrepancy was found in the design documents, so we send the following query. ■ Query No. [Number] ■ Subject Drawings [Example: A-201 2nd Floor Plan], [Example: S-202 2nd Floor Beam Framing Plan] ■ Query Content [Example: Regarding the floor of the 2nd floor restroom, the architectural drawing indicates a slab depression of 50 mm, but there is no mention in the structural drawing. Which should we take as governing?] ■ Contractor's Proposal [Example: To secure the floor drainage slope, we propose constructing the slab with a 50 mm depression as shown in the architectural drawing.] ■ Desired Response Date By [Month/Day] ([Example: In order to start 2nd floor slab rebar placement]) We attach the drawing with redline markups at the relevant location. We apologize for the trouble, and appreciate your reply.

Writing Tips & Notes

Group queries together rather than sending them one by one. Attach drawings with clear redline markups, and always include the contractor's proposed solution—designers appreciate concrete options.