Mechanical & Manufacturing Japanese · 時間がかかった段取り替えを班長と振り返る

Reviewing Slow Die Changeover with Team Leader

This morning's press die changeover took 75 minutes, causing the line to fall behind schedule. At the end of the shift, you and your Team Leader review a video recording step-by-step to identify time waste and tasks that can be converted to external setup (external changeover).

Other (H)

This morning's changeover took 75 minutes. Let us review together what happened.

Me

Yes. I recorded it on video, so let us review while watching.

Me

First, searching for the die took 15 minutes, because its storage location had not been decided.

Other (H)

That is a waste. Let us decide on a location for the dies and assign numbers.

Me

Also, tightening tools were missing, so I had to walk over to the neighboring line to borrow them.

Other (H)

We need to have the tools prepared for each line. What else was there?

Me

After the die exchange was finished, the operator went to fetch material for the next run. That is work that can be done before stopping the machine.

Other (H)

Exactly. That can be converted to external setup.

Me

If we prepare the die, material, and tools before stopping the machine, I believe the changeover time can be cut by about half.

Other (H)

Then let us review the changeover sequence and rewrite the standard work procedure sheet.

Me

Yes. Next week I will test the new procedure and measure the time. I will record the results in the daily report.

Other (H)

Please do. If it goes well, let us roll it out to the other press machines as well.

Key Patterns

  • Stating how much time a specific operational step consumed
  • Recounting the sequence of actions to highlight tasks done out of order
  • Identifying tasks that can be performed prior to equipment shutdown
  • Stating prerequisite preparations and their projected time-saving outcome