Mechanical & Manufacturing Japanese · 課長に改善提案を説明する

Presenting Kaizen Proposal to Section Manager

On the assembly line last month, missing washers occurred 3 times. You present a poka-yoke proposal using sensors to your Section Manager: problem statement, technical solution, cost, quantified benefits, and horizontal deployment potential.

Me

Section Manager, regarding the Kaizen proposal I mentioned earlier, could you spare about 5 minutes?

Other (L)

Sure. It was about the missing washer issue, right?

Me

Yes. Last month on the assembly line, there were 3 cases of missing washers. All were caught during final inspection, so none escaped to customers.

Me

Therefore, I would like to install a poka-yoke that uses a sensor to verify the presence of a washer before bolt tightening.

Other (L)

How much will the cost be?

Me

It will be about 80,000 yen for the sensor and wiring. If we ask maintenance for installation, it can be completed in half a day on Saturday.

Other (L)

Can you quantify the expected benefit in numbers?

Me

If missing washers are eliminated, man-hours for rework and re-inspection are projected to decrease by about 4 hours per month.

Other (L)

Could this be horizontally deployed to other lines as well?

Me

I believe it can be used on Line 2, which has identical assembly operations. I will investigate that line and add it to the proposal.

Other (L)

Understood. Show me the proposal once completed. Let us bring it up at next week's Kaizen meeting.

Me

Thank you very much. I will submit it by Wednesday.

Key Patterns

  • Asking a supervisor for a short block of time to discuss a matter
  • Stating a proposed technical solution after explaining the problem
  • Breaking down costs into specific items and total estimate
  • Stating projected efficiency improvements with concrete numbers

Source

Authored by GoMe