Construction Japanese · 定例会議で工程を報告する

Reporting Construction Progress at the Weekly Meeting with the Owner

At the regular weekly coordination meeting with the project owner and design supervisor, you present structural framing and interior finishing progress updates. You urge the client to finalize exterior tile color selections promptly, as exterior facade works lie directly on the project critical path.

Other (K)

Now, please present the construction schedule progress report.

Me

Yes. Please refer to the weekly schedule chart in your handout.

Me

For the structural frame, concrete placement up to the 6th floor slab has concluded on schedule. Next week, we will commence operations on the 7th floor.

Me

Regarding interior fit-out, ceiling substrate framing has begun on the 4th floor.

Other (M)

Has the 4th floor finished ceiling height been executed strictly according to our recent engineering inquiry response?

Me

Yes, we modified it to 2,600 in accordance with the response and revised the shop drawings accordingly. The craftsmen have been notified as well.

Other (K)

When will we be able to review material samples for the entrance lobby finishes?

Me

At the next regular progress meeting, we will bring stone and tile finish samples.

Me

Additionally, it would be extremely helpful if the exterior tile color could be finalized within this month.

Me

Because exterior finishes lie on the critical path, if the color remains unconfirmed, procurement orders for tiles will not be completed in time.

Other (K)

Understood. I will confirm internally within our company and provide our response by next week.

Other (M)

Once the color is selected, please submit the comprehensive submittal approval drawings as well.

Me

Understood. I will compile today proceedings into official meeting minutes and distribute them tomorrow.

Key Patterns

  • Inviting meeting attendees to refer to distributed handout materials
  • Reporting that a key structural milestone has concluded on schedule
  • Politely requesting an expeditious decision from the client side
  • Explaining the critical project impact if a key milestone decision is delayed