Construction Japanese · 月末に協力会社の出来高を査定する

Reviewing Completed Work with the Subcontractor at Month-End

Before the cutoff date, the formwork subcontractor representative brings the records of work completed this month. You cross-check them against the quantities verified on site, determine the approved percentage, and handle unsigned daywork slips.

Other (C)

Hello. I brought the records of work completed this month.

Me

Hello. Tomorrow is the cutoff date. Let me take a look.

Me

Formwork is listed as completed up to the 5th floor, making the completed progress 60% of the total, right?

Other (C)

Yes, because operations are advancing strictly according to the progress schedule.

Me

However, on the 5th floor, column formwork is still partially remaining. From what I saw on site, the 5th floor is at about 80%.

Other (C)

Is that so? We anticipate completing that early next week though...

Me

In that case, please put the remainder into next month's completed work. For this month, I will assess the 5th floor at 80%.

Other (C)

Understood. Additionally, we have included last week daywork force-account labor as well.

Me

Regarding daywork labor, I only approve slips that bear my physical signature. These two slips lack a signature. What work was involved?

Other (C)

Site cleanup and debris removal. The project director requested it from us directly.

Me

Understood. I will confirm with the project director, and if there are no objections, include it in this month billing. Please submit the revised invoice by tomorrow afternoon.

Other (C)

Understood. Thank you very much for your cooperation.

Key Patterns

  • Restating figures submitted by the counterparty to verify billing assertions
  • Cross-referencing submitted paperwork against physical site observations
  • Directing the counterparty to push uncompleted portions into the next pay period
  • Stipulating mandatory compliance criteria (e.g., signature) for claim approval