Construction Japanese · ヒヤリハット報告書

Near-Miss Incident Report

Japanese Text

ヒヤリハット報告書

報告日:〔〇月〇日〕
報告者:〔名前〕(〔会社名〕・〔職種〕)

■いつ
〔〇月〇日〕〔午前10時〕頃

■どこで
〔例:4階 東側 外部足場〕

■何をしていたとき
〔例:型枠材を肩に担いで、足場の上を運んでいたとき〕

■何が起きたか
〔例:足場の通路に置いてあった番線に足を取られ、転びそうになった。手すりにつかまったので、けがはなかった。〕

■分類
〔例:転倒(つまずき)〕

■原因と思われること
〔例:前日に使った番線が片付けられず、通路に残っていた。材料を担いでいて、足元が見えなかった。〕

■対策(案)
〔例:作業終了時に、足場の通路に物が残っていないか職長が確認する。長い材料は二人で運ぶ。〕

■確認
職長:〔名前〕 元請担当:〔名前〕

Structure Breakdown

Record the company and trade to identify which crews encounter specific hazards and deliver targeted guidance. Naming the reporter facilitates follow-up questions rather than assigning fault.
Detail the precise work activity underway. Countermeasures differ greatly between carrying heavy materials versus walking unencumbered when a trip occurs.
Describe objectively what occurred and why it stopped short of injury. The grammatical pattern ~そうになった ("almost happened") is quintessential to near-miss reports. Internal logs use plain form (~た) rather than formal honorifics.
Classify the event using official Ministry of Health, Labour and Welfare injury accident type categories: falls from height, trips on same level, impacts, flying/falling objects, caught in/between. Standard classification enables statistical analysis of recurrent hazards.
Identify hazardous site conditions (unorganized materials, poor lighting, obstructed sightlines) rather than stopping at personal carelessness.
Formulate actionable proposals specifying who acts and when. Designated as proposed (案) because official measures are finalized with site foremen and management, then shared in morning assemblies or KY meetings.
Signed confirmation by both trade foreman and general contractor supervisor confirms review. Unread reports discourage field personnel from reporting future hazards.

English Translation

Near-Miss Incident Report Report Date: [Month/Day] Reporter: [Reporter Name] ([Company Name], [Trade/Craft]) ■ When Around [10:00 AM] on [Month/Day] ■ Where [Example: 4th floor exterior scaffolding, east side] ■ Activity at the Time [Example: Carrying formwork lumber on shoulder along the scaffold walkway] ■ What Happened [Example: Foot caught on binding wire left in the scaffold walkway, almost tripped and fell. Caught hold of the handrail, so no injury occurred.] ■ Incident Classification [Example: Fall on same level (tripping)] ■ Probable Root Cause [Example: Binding wire used the previous day was not cleared and remained in walkway. Carrying lumber obstructed forward view of footing.] ■ Proposed Countermeasures [Example: Foreman inspects scaffold walkways at end of shift to confirm no objects remain. Two workers carry long materials together.] ■ Verification Foreman: [Foreman Name] General Contractor In-Charge: [In-Charge Name]

Writing Tips & Notes

Complete the report on the same day with maximum detail: exact location, object involved, and height. Filing a near-miss report is not about assigning blame—it enables site-wide correction before someone suffers a real injury.

Source

Authored by GoMe