Dandori Hachibu (段取り八分): Preparation Is Eighty Percent of the Work

The rigorous Japanese site philosophy of advance preparation illustrated through a major concrete placement day, and the key phrases you will hear when asked "Is preparation complete?".

Eighty Percent Preparation, Twenty Percent Execution

Dandori (段取り) signifies advance planning, sequencing, and preparation for construction work. Professionals in the Japanese building industry frequently quote the proverb "Dandori hachibu, shigoto nibu" (段取り八分、仕事二分): thorough preparation accomplishes eighty percent of the assignment in advance. This maxim explains why Japanese site engineers dedicate substantial time to progress schedules, coordination meetings with trade subcontractors, and inspection checklists—tasks that novices often dismiss as mere paperwork.

Key Vocabulary

段取りだんどり
Dandori: advance sequencing, scheduling, and preparatory logistics for construction tasks
打ち合わせうちあわせ
Uchiawase: concise, practical coordination meeting held between site supervisors and craft trades
手待ちてまち
Temachi: workers or equipment forced into idle standby due to missing materials, drawings, or inspections

Case Study: The Day of a Structural Concrete Pour

A concrete placement day actually commences a week prior. Reinforcing steel inspections must be concluded with formal sign-off from the supervising architect; electrical sleeves and MEP floor penetrations must be solidly anchored; concrete pump trucks and agitator truck staging zones must be reserved, including public road occupancy permits where required. On the prior afternoon, the site engineer conducts a coordination meeting with the concrete placement foreman, pump operator, and floor finishing crew: confirming exact arrival times, pouring sequence, test cylinder sampling protocols, and rain tarpaulin contingency plans. On the actual pour day, the sole remaining duty is monitoring concrete truck turnarounds and verifying mix quality at discharge.

Phrases You Will Hear on Site

Eighty percent preparation, twenty percent execution.

Are preparations for tomorrow all in order?

Please make sure skilled workers are not kept waiting idle.

Habits of Effective Planning Engineers

At the end of each day, review the master progress schedule to determine requirements for tomorrow and the upcoming three days, then walk the jobsite to verify physical conditions with your own eyes. Place phone calls to reconfirm scheduled material delivery windows rather than blindly trusting initial booking confirmations. Maintain contingency plans for inclement weather. And whenever a potential delay is detected, inform trade contractors promptly so they can reallocate personnel—delaying notification unfairly offloads the cost of poor preparation onto partners.