What does 週間工程表(しゅうかんこうていひょう) mean in Japanese?

Weekly schedule

Terms: 週間工程表
Terms週間工程表
Readingしゅうかんこうていひょう
English MeaningWeekly schedule
LevelCore
Specialty AreaConstruction & Schedule Management
SpecialtyConstruction Japanese

Technical Explanation

A detailed weekly look-ahead schedule prepared by the general contractor, coordinating day-by-day operations, crew headcounts, trade work zones, and shared equipment utilization (cranes, concrete pump trucks) for the upcoming week.

Practical Notes

Distributed at weekly multi-trade meetings (週間工程会議). Kept alongside monthly look-aheads (月間工程表) and master project schedules (全体工程表).

Workplace Examples

Please distribute the weekly schedule for next week by Friday.

I noted the days when the crane will be utilized in the weekly schedule.