Construction Japanese · Building Services (M&E)
What does 消防検査 mean in Japanese?
Fire department inspection, official fire safety inspection
| Terms | 消防検査 |
|---|---|
| Reading | しょうぼうけんさ |
| English Meaning | Fire department inspection, official fire safety inspection |
| Level | Common |
| Specialty Area | Building Services (M&E) |
| Specialty | Construction Japanese |
Technical Explanation
An official statutory completion inspection conducted by local fire marshals once fire protection systems are fully installed: verifying detector tripping, sprinkler water discharge, hydrant flow pressure, and exit sign illumination. In principle, installation completion notifications (secchi todoke) must be filed within 4 days of work completion (Fire Service Act Enforcement Regulations Article 31-3) prior to inspection; passing this inspection is mandatory prior to building handover and occupancy.
Practical Notes
General contractors conduct rigorous in-house pre-inspections (jishu kensa) across every fire device before hosting official fire marshals.
Workplace Examples
消防検査の前日までに、感知器の作動試験を全部終わらせてください。
Please complete all detector operational tests by the day before the fire department inspection.
消防検査で指摘された点を、来週までに是正します。
We will rectify the issues identified during the fire department inspection by next week.