What does クリティカルパス mean in Japanese?

Critical path

Terms: クリティカルパス
Termsクリティカルパス
Readingクリティカルパス
English MeaningCritical path
LevelAdvanced
Specialty AreaConstruction & Schedule Management
SpecialtyConstruction Japanese

Technical Explanation

The longest continuous chain of dependent activities from start to completion in a project schedule that possesses zero total float. Any delay to an activity situated along the critical path immediately delays the overall completion date of the entire building.

Practical Notes

Site managers focus rigorous attention on critical path operations (e.g., excavation, deep foundations, structural concrete frames).

Workplace Examples

Because foundation work is an activity situated along the critical path, if it is delayed, completion will also be delayed.