IT Japanese · 進捗遅れによる納期遅延の懸念を上司に報告する

Reporting Critical Schedule Delays and Requesting Deadline Adjustments

Tomorrow is the scheduled completion date for integration testing, but unforeseen errors in external service integrations have left about 30 items pending. You honestly report remaining items to your lead, propose priorities, request extra staffing, and present a new delivery date.

Me

Mr. Tanaka, I have an urgent matter I need to consult with you about regarding integration testing progress.

Other (L)

Tomorrow is the scheduled test completion date, right? Did something happen?

Me

Yes. Unexpected errors have occurred frequently in external service integration test cases, leaving approximately 30 items pending.

Other (L)

30 items? At this pace, we won't make it by tomorrow.

Me

I apologize. As things stand, completing them by tomorrow evening will be very difficult.

Me

I will prioritize the payment-related tests; could we request one additional person to support the remaining display-related tests? With extra help, we project we can finish by the day after tomorrow morning.

Other (L)

Understood. I will have Mr. Sato join in starting this afternoon. Let's decide by the end of today what will be covered.

Key Patterns

  • I have an urgent matter I need to consult with you about regarding ~ (Opening phrase when consulting urgently with a supervisor about schedule or progress)
  • As things stand, it will be very difficult to ~ (Clearly stating that completing on schedule is unlikely under current conditions)
  • Could we request one additional person to support ~? (Politely requesting temporary backup personnel)